Can you dig, fill or clear a wetland on your own property?

What Section 404 requires before fill goes into a wetland, the exemptions, who issues permits, and how Michigan, Wisconsin, New York and Ohio add to it.

Updated November 25, 2026 · 8 official sources
On this page: 6 sections
  1. 1Does owning the land remove the permit requirement for filling or clearing a wetland?
  2. 2Which digging, filling or clearing in a wetland is exempt from the federal permit?
  3. 3Who issues the wetland fill permit, and when is a general permit enough?
  4. 4Do state rules add to the federal permit for wetlands?
  5. 5How do I find out whether my land has a regulated wetland?
  6. 6What must a landowner show before a permit to fill a wetland is granted?

No: Section 404 of the Clean Water Act requires a permit before dredged or fill material may be discharged into waters of the United States unless the activity is exempt, and in Ohio, wetlands on public or private land may be considered waters of the U.S..1-2

Does owning the land remove the permit requirement for filling or clearing a wetland?

Section 404 of the Clean Water Act establishes a program to regulate the discharge of dredged or fill material into waters of the United States, including wetlands.1 A wetland is an area of land where water covers the soil or is present at or near the surface of the soil.2 In Ohio, anyone who wants to place fill material into a wetland must obtain proper permits first, and proposed activities within wetlands on both private and publicly owned land may be regulated by both Ohio EPA and the U.S. Army Corps of Engineers. Fill material, as Ohio EPA uses the term, includes any type of rock, sand, soil or clay.2 Under Section 404, a U.S. Army Corps of Engineers permit is required for the discharge of dredged or fill material into waters of the United States.3

Which digging, filling or clearing in a wetland is exempt from the federal permit?

Certain activities are exempt from permit requirements under Section 404(f)(1) of the Clean Water Act. A Section 404 permit is generally not needed when discharges of dredged or fill material are associated with normal farming, ranching or silviculture activities such as plowing, cultivating, minor drainage and harvesting, and the exemption pertains to activities that are part of an established, ongoing farming or forestry operation. The exempt activities on EPA's list also include construction and maintenance of farm or stock ponds, construction and maintenance of irrigation ditches, and maintenance but not construction of drainage ditches.4

The exemptions have limits. In general, any discharge of dredged or fill material associated with an activity that converts a wetland to upland is not exempt and requires a Section 404 permit. Activities that bring a wetland into farm production where the wetland has not previously been used for farming are not considered part of an established operation and therefore require a permit.4 A landowner can find out whether a specific activity is exempt by contacting the local U.S. Army Corps District office or EPA regional office.4

Who issues the wetland fill permit, and when is a general permit enough?

The U.S. Army Corps of Engineers administers the day-to-day Section 404 program, including individual and general permit decisions. An individual permit is required for potentially significant impacts, and individual permits are reviewed by the Army Corps or an approved State or Tribal 404(g) Program under a public interest review. For most discharges that will have only minimal adverse effects, a general permit may be suitable, and general permits are issued on a nationwide, regional or state basis for particular categories of activities.1

Nationwide Permits are issued by the Army Corps to authorize certain activities that have minimal individual and cumulative adverse effects on the aquatic environment.5 In the Corps' New York District, some nationwide permits also require pre-construction notification to the Corps before any activities begin, and a Standard Individual Permit is required if a project does not fall under the criteria for a general permit or letter of permission. When a project requires an individual permit, the Corps issues a Public Notice advising all interested parties of the proposed activity.3

Do state rules add to the federal permit for wetlands?

Four states' pages show how a state rule can sit beside Section 404. In Ohio, a wetland that is not considered a water of the U.S. still may be considered a water of the State of Ohio, and placing dredged or fill material into an isolated wetland in Ohio requires an isolated wetland permit from Ohio EPA.2 Michigan law requires that persons planning to conduct certain activities in regulated wetlands apply for and receive a permit from the state before beginning the activity, and Michigan received federal authorization in 1984 to administer Section 404 in most areas of the state.6 In Wisconsin, landowners and developers are required to avoid wetlands with their projects to the extent practicable.7 The table covers Michigan, Wisconsin, New York and Ohio, and other states have their own rules.

State What the state regulates
Michigan A state permit is required to deposit or permit the placing of fill material in a wetland, to dredge or remove soil or minerals from a wetland, and to drain surface water from a wetland. A wetland not connected to one of the Great Lakes, Lake St. Clair, or an inland lake, pond, stream or river is regulated if the wetland is more than 5 acres in size6
Wisconsin Activities that typically require a DNR wetland permit include placing dredged or fill materials into a wetland, removing material from a wetland, earthwork that changes the grade or contours of the land, and mechanized land clearing of shrubs or trees from wetlands by bulldozing or grubbing and removing the root structures7
New York Almost any activity which may adversely impact the natural values of the wetlands or their adjacent areas is regulated, placement of fill, excavation or grading included. A 100 foot adjacent area, measured horizontally from the wetland boundary, is also regulated. As of January 1, 2025, a wetland must be at least 12.4 acres in size or regulated as a wetland of Unusual Importance for protection under the Freshwater Wetlands Act8
Ohio Discharging dredged or fill material into waters of the U.S. may require a Section 404 permit from the Army Corps and a Section 401 Water Quality Certification from Ohio EPA, and fill in an isolated wetland requires an isolated wetland permit from Ohio EPA2

How do I find out whether my land has a regulated wetland?

Individuals uncertain about the status of waters on their property may request a jurisdictional determination from the U.S. Army Corps of Engineers.3 The state pages add their own routes.

In Ohio, a qualified wetland professional with knowledge of soils and plant species evaluates a property by performing a wetland review, also known as a wetland delineation. An Ohio owner who would like someone to review the property before hiring a professional can contact the local soil and water conservation district, and each Ohio county has its own district. The Ohio delineation report is submitted to the Army Corps for review and approval, and the Army Corps makes the final determination whether the area is a wetland.2

Wisconsin's DNR Storm Water, Waterway, and Wetland Permit Viewer screens a property for wetlands and any previous delineations or permits, though the Wisconsin maps are not 100% accurate and wetland plants, hydrology indicators and soils may still indicate wetland presence. A Wisconsin landowner can request the DNR Wetland Identification Service to obtain a presence/absence statement and an approximate wetland boundary.7

In New York, the only way to confirm the presence or absence of a freshwater wetland regulated by DEC is to receive a jurisdictional determination, and New York's informational wetland maps cannot be relied upon to determine the presence or absence of regulated freshwater wetlands. After a request for a jurisdictional determination is made, New York's DEC has 90 days to provide a determination letter, which is effective for 5 years after the date of issuance.8

What must a landowner show before a permit to fill a wetland is granted?

A Section 404 permit applicant must first show that steps have been taken to avoid impacts to wetlands, streams and other aquatic resources, that potential impacts have been minimized, and that compensation will be provided for all remaining unavoidable impacts. No discharge of dredged or fill material may be permitted if a practicable alternative exists that is less damaging to the aquatic environment.1 In the Corps' New York District, mitigation is typically required for permanent wetland losses over 0.1 acres and will be evaluated on a case-by-case basis.3 In Wisconsin, wetland mitigation is required for all wetland impacts authorized in an individual permit.7 New York applicants are generally required to examine alternative sites and project designs that avoid and reduce impacts to wetlands, and to develop plans to create or improve wetlands or wetland functions to compensate for unavoidable impacts.8

EPA's Section 404 pages, U.S. Army Corps of Engineers permit pages, and the wetland pages of Michigan, Wisconsin, New York and Ohio, checked November 2026.

Sources (8)

  1. EPA: Permit Program under CWA Section 404, read November 25, 2026 ↑
  2. Ohio EPA Division of Surface Water: Know Before You Build, read November 25, 2026 ↑
  3. U.S. Army Corps of Engineers New York District: Obtaining a Permit, read November 25, 2026 ↑
  4. EPA: Exemptions to Permit Requirements under CWA Section 404, read November 25, 2026 ↑
  5. U.S. Army Corps of Engineers: Nationwide Permits, read November 25, 2026 ↑
  6. Michigan EGLE: State and Federal Wetland Regulations, read November 25, 2026 ↑
  7. Wisconsin DNR: Wetland Permitting, read November 25, 2026 ↑
  8. New York State DEC: Freshwater Wetlands Permits, read November 25, 2026 ↑

Find contractors in your county

Request a quoteSmart search