How many days before digging do you have to call 811?

The notice five states require before digging, what days count toward it, and how long a locate request stays good in each.

Updated November 25, 2026 · 5 official sources
On this page: 8 sections
  1. 1How many days before digging do you have to call 811 in each state?
  2. 2How many days before digging must Washington excavators call 811?
  3. 3How many days before digging must Pennsylvania excavators call 811?
  4. 4How many days before digging must Florida excavators give notice?
  5. 5How many days before digging must Iowa excavators call 811?
  6. 6How many days before digging must Virginia excavators call 811?
  7. 7Does 811 cost money, and can you get fined for digging without calling?
  8. 8Do you have to call 811 before digging by hand?

Washington requires a call to 811 at least two business days before digging, Pennsylvania requires three business days, and Florida requires 2 full business days before excavation that is not beneath the waters of the state.1-3 In Iowa, the request should be made at least two days ahead, excluding Saturday, Sunday and legal holidays.4

How many days before digging do you have to call 811 in each state?

To comply with Iowa's One Call law, a homeowner or excavator must go online or call 811 or 800-292-8989 to schedule underground utility lines to be located and marked, and the request creates a ticket for the location to be visited.4 A Virginia excavator shall only commence work after confirming on the notification center's positive response system that each operator has marked its utility lines, reported that its utility lines are not present in the area, or otherwise posted a positive response indicating excavation may begin, or if informed by the notification center that no operators are to be notified, and Virginia's statute sets apart emergencies and one unmarked line case.5

The table covers Washington, Pennsylvania, Florida, Iowa and Virginia, and other states have their own rules:1-5

State Notice before digging and how long the request stays good
Washington At least two business days before digging, excluding Saturday, Sunday and legal holidays, under RCW 19.122. Excavators maintain their marks for 45 days or until the project is complete, whichever is shorter1
Pennsylvania At least three business days before starting any excavation project2
Florida Not less than 2 full business days before excavation or demolition that is not beneath the waters of the state, and not less than 10 full business days before excavation or demolition that is beneath the waters of the state. The information is valid for 30 calendar days3
Iowa The request should be made at least two days before starting any digging or excavating project, excluding Saturday, Sunday and legal holidays4
Virginia Any scheduled excavation date is not less than 48 hours nor more than 12 working days from the date of the locate request. The notification is valid for 15 working days from 7:00 a.m. on the next working day following a locate request or 15 working days following a scheduled excavation date, whichever is later5

How many days before digging must Washington excavators call 811?

Washington's Dig Law is RCW 19.122, and complying with the law means calling 811 or making the request online at least two business days before digging, with Saturday, Sunday and legal holidays excluded. Under the Dig Law, Washington excavators must give two to ten full business days notice before the scheduled work-to-begin date and mark the excavation area with white lining. Effective January 1, 2026, a Washington excavator may not begin excavation until a positive response has come from all operators with underground facilities in the area identified in the notice. Washington facility operators must respond to requests for locates prior to the work-to-begin date and, once marking is complete, provide a positive response to the one number locator service. Washington excavators must maintain their marks for 45 days or until the project is complete, whichever is shorter, and a project that continues past 45 days needs a call for a new locate.1

How many days before digging must Pennsylvania excavators call 811?

Pennsylvania homeowners and contractors must call 811 at least three business days before starting any digging or excavation project, as required by law. The contact goes to Pennsylvania's one call system, by calling 811 or submitting a request online, at least three business days before starting any excavation project. Pennsylvania's one call system then alerts facility owners of the intent to dig so the owners can mark their buried lines. Underground power lines, communication cables, gas lines, water lines or other utilities may lie below the surface of a property or an area of planned excavation. The PA PUC's advice is to allow time for utility companies to visit the area to mark the location of their underground facilities, and the markings give a clear guide of what to avoid when excavating.2

How many days before digging must Florida excavators give notice?

Florida's statute requires an excavator to provide notice through the state's notification system not less than 2 full business days before beginning any excavation or demolition that is not beneath the waters of the state, and not less than 10 full business days before beginning any excavation or demolition that is beneath the waters of the state. Business days in Florida's statute are Monday through Friday, excluding the holidays the statute lists, and a listed holiday that falls on a Saturday is observed on the preceding Friday. A notification the Florida system receives at any time other than during business hours is considered received at the beginning of the next business day. The information a Florida excavator provides includes the commencement date and anticipated duration of the excavation or demolition, whether machinery will be used and the approximate depth of the excavation. Information provided by a Florida excavator is valid for 30 calendar days after the date the information is provided to the system.3

How many days before digging must Iowa excavators call 811?

In Iowa, the request to locate and mark lines should be made at least two days before starting any digging or excavating project, excluding Saturday, Sunday and legal holidays. After the Iowa request, operators who have underground facilities in the planned excavation area are notified, including natural gas and power utilities, communications companies and city utility departments. Within 48 hours of being contacted, Iowa utility representatives either mark their underground facilities with color-coded paint marks or flags or report that there are no lines in the area. The color of the flags or paint tells Iowa excavators what type of utility is in the area: red marks electric power lines, cables, conduit and lighting cables, and yellow marks natural gas, oil, steam, petroleum or other gaseous or flammable material.4

How many days before digging must Virginia excavators call 811?

Virginia's Underground Utility Damage Prevention Act bars any person from making or beginning an excavation or demolition without first submitting a locate request to the notification center. Any scheduled excavation date in Virginia shall not be less than 48 hours nor more than 12 working days from the date of the locate request. A working day in Virginia's act is every day except Saturdays, Sundays and legal state and national holidays, and a locate request made on a day that is not a working day is considered submitted on the next working day at 7:00 a.m.. Unless the excavator provides a scheduled excavation date or extraordinary or exigent circumstances prevent it, a Virginia operator or contract locator shall mark the line and report the marking status to the positive response system by no later than 7:00 a.m. on the third working day following the locate request. A Virginia excavator's notification is valid for 15 working days from 7:00 a.m. on the next working day following a locate request or 15 working days following a scheduled excavation date provided to the notification center, whichever is later. Three working days before the end of the 15-working-day period, or at any time when line-location markings on the ground become illegible, the Virginia excavator intending to excavate shall contact the notification center and request the re-marking of lines.5

Does 811 cost money, and can you get fined for digging without calling?

Washington's locating service is provided free to the excavator, and Iowa's one call service is free as well.1, 4 Florida's statute requires a free-access notification system with a single toll-free telephone number within the state that excavators can use.3

Hitting an underground utility while digging in Washington can cause serious injuries, lead to utility outages that disrupt service to entire neighborhoods, and can potentially result in fines and costly repairs.1 Hitting an underground utility line while digging in Iowa can result in fines and repair costs, the Office of the Attorney General enforces Iowa's One Call Law, and a complaint about a violation can be filed with the Iowa Utilities Commission.4 In Virginia, except for counties, cities and towns, an excavator who willfully fails to submit a locate request is liable to the operator whose facilities that excavator damages for three times the cost to repair the damaged property, provided that the operator is a member of the notification center, and the punitive damages awarded under that section shall not exceed $10,000 in any single cause of action.5

Do you have to call 811 before digging by hand?

Iowa law requires the location of all underground utility lines to be marked before digging by hand or with equipment.4 Virginia's act does not apply to any hand digging performed by an owner or occupant of a property, or to the tilling of soil for agricultural purposes.5 In Washington, a locate must be requested when installing any type of sign, including real estate and political signs, and residential yards and right-of-way have numerous underground utility lines that can be damaged when installing a sign.1 Pennsylvania's three business day requirement names homeowners and contractors and applies before any digging or excavation project.2

Washington's Dig Law page, the Pennsylvania PUC's 811 page, Florida Statutes chapter 556, the Iowa Utilities Commission's One Call page and the Code of Virginia, checked November 2026.

Sources (5)

  1. Washington UTC: Dig Law, read November 25, 2026 ↑
  2. PA PUC: PA One Call - 811, read November 25, 2026 ↑
  3. The Florida Senate: Chapter 556 - 2026 Florida Statutes, read November 25, 2026 ↑
  4. Iowa Utilities Commission: Iowa's One Call Law, read November 25, 2026 ↑
  5. Code of Virginia: Chapter 10.3. Underground Utility Damage Prevention Act, read November 25, 2026 ↑